US Route 50 HOV Lanes Phase 0

Description: In El Dorado County on Rte 50 at the El Dorado Hills boulevard Interchange. Reconstruct westbound off-ramp and westbound on-ramp with a dedicated HOV bypass lane and ramp metering.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Placerville
Zip Code 95667
 
Senate District
01
Assembly District 05
Congressional District 04
 
Caltrans District
03
 
 
County/State Route El Dorado 50
Postmile Begin/End 0.2 1.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  947    1,119  
Lane Miles Added (HOV)  0.25    0.25  
Lane Miles Added (Mixed)  0    0  
Peak Period Time Savings (minutes)  22.728    81,685  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
El Dorado County John Kahling (530)621-4974   john.kahling@edcgov.us
Design (PS&E) Phase
El Dorado County John Kahling (530)621-4974   john.kahling@edcgov.us
Right of Way Phase
El Dorado County John Kahling (530)621-4974   john.kahling@edcgov.us
Construction Phase
El Dorado County John Kahling (530)621-4974   john.kahling@edcgov.us
 
Corridor System Management Plan
El Dorado County Paul Horn (530)6215925   paul.horn@edcgov.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$15,500 $0 $15,500
Non-bond Funding
Local**
$3,700 $0 $3,700
 
Total**** $19,200 $0 $19,200

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $500 $500 $501
Design(PS&E)
$1,910 $-500 $1,410 $1,322
Right of Way
$50 $0 $50 $104
Construction
$17,240 $0 $17,240 $15,837
 
Total* $19,200 $0 $19,200 $17,764

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
06/01/1999 

06/09/2000 
06/01/1999 

06/09/2000 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/16/2012 

04/23/2012 
 

 
01/16/2012 

04/23/2012 
100  01/02/2012 

05/11/2012 


-1 
Begin Right of Way Phase

End Right of Way Phase
02/06/2012 

04/23/2012 
 

 
02/06/2012 

04/23/2012 
100  01/02/2012 

05/11/2012 


-1 
Begin Construction Phase

End Construction Phase
07/17/2012 

12/31/2013 
 

 
07/17/2012 

12/31/2013 
100  08/07/2012 

03/31/2014 
-1 

-3 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

10/31/2014 
 

 
01/01/2014 

10/31/2014 
05/01/2014 

12/31/2018 
-4 

-51 
Corridor System Management Plan
Adoption Date 05/01/2009    05/01/2009  05/01/2009 
Implementation Date 07/01/2010    07/01/2010  06/03/2009  13 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 947 1,119
Lane Miles Added (HOV) 0.25 0.25
Lane Miles Added (Mixed) 0 0
Peak Period Time Savings (minutes) 22.728 81,685

Bond Funding Cost
Adopted:
$15,500,000
Current Approved:
$15,500,000
Actual Expenditures:
$14,716,000

 

Status as of December 31, 2023.